BMI Domestic Lounge Heathrow Terminal 1Client / Project / Location
BMI / Domestic Departure lounge / Heathrow Terminal 1. Role / Service
Angelo Zenga HCL project manager. John Gray HCL M&E manager. Project Details
Lounge Envelope, M&E installation, Flooring, Ceilings, Decs, Specialist joinery & FFE sourcing. Programme
4 weeks from accepting the Shell & Core area to finished area ready for occupation. Programme Constraints
Lead-in of joinery items reduced due to in-house sourcing. 2 phases upstairs & downstairs. Value
Overall project value: £800k. Procurement system or method
Negotiated based on construction drawings. Established Supply chain
All works completed using directly employed staff. Learning
|
Related Projects
Other Projects with the same keywords:
AIRPORT LOUNGES- British Airways CIP Lounge Gatwick North Terminal
- Gulf Air Lounge Heathrow Terminal 3
- Malaysian Airlines Heathrow Terminal 3
- KLM Holideck Heathrow Terminal 4
- Virgin Departures Lounge Interim Refurbishment Heathrow Terminal 3
- British Airways CIP Lounge Gatwick North Terminal
- Gulf Air Lounge Heathrow Terminal 3
- Malaysian Airlines Heathrow Terminal 3
- KLM Holideck Heathrow Terminal 4
- Virgin Departures Lounge Interim Refurbishment Heathrow Terminal 3
- BAA Visitors Centre
- Lounge Maintenance & Specialist Projects
- DTZ - Cardinal Point
- Gulf Air Lounge Heathrow Terminal 3
- Malaysian Airlines Heathrow Terminal 3
- WBC 1 HAL MD Office Refurbishment
- Heathrow T3 Landside Catering
- KLM Holideck Heathrow Terminal 4
- SAA Departures & Arrivals Lounges Interim Refurbishment
- WBC 1 Ground & 1st Floor Refurbishment
- Virgin Departures Lounge Interim Refurbishment Heathrow Terminal 3
- Building 941
- Heathrow T1 Plaza Retail Reconfiguration