Malaysian Airlines Heathrow Terminal 3

Client / Project / Location

Malaysian Airlines / Departures Lounge / Heathrow Terminal 3

Role / Service

Angelo Zenga HCL Project Manager.

John Gray HCL M&E Manager.

Project Details

Lounge Envelope, M&E installation, Flooring, Ceilings, Decs, Specialist Joinery & FFE.

Programme

4 weeks from strip-out finished area ready for occupation.

Programme Constraints

Lead-in of joinery items. (Reduced due to in-house sourcing).

Value

Overall project value: £ 85K.

Procurement system or method

Negotiated based on construction drawings.

Established Supply chain

All works completed using directly employed staff.

Learning

  • Early involvement
  • Pre planning
  • Early order and manufacture of materials & product.